Leicester Cathedral - November 2014
Posted by Yuli Lee / 21st November 2014

Leicester Cathedral - November 2014

Visit to Site - 20th November 2014

Underfloor heating pipes are being positioned and clipped in for Limecrete Screed to be placed. The screed cannot be trafficked for 1 week, so it was agreed with FWA to swap around tasks to progress the joinery, until the screed is sufficiently dried out for the stone slabs to be laid.