A couple of months since Messenger’s site set-up, and their dismantling and removal of the 1930’s Old Song School building, we visit site to understand what is removal has revealed and to see our site for our new building, and to understand the interfaces with the historic cathedral

By the time of our next visit, large areas of ...
Read more
The good weather finds Northfield making good progress with the ...
Read more
The new stone floor is intended to provide a hard-wearing ...
Read more
By June almost all the scaffolding inside the cathedral has ...
Read more
With the underfloor heating loops complete and tested and at ...
Read more
Having walked from the station as usual, we are cheered ...
Read more
Almost a year after it was programmed, and following the ...
Read more
Later in March we are asked to make a second ...
Read more
By March the bulk of the redecoration work to the ...
Read more
By December the scaffold has been removed from the south ...
Read more
During the long period of gaining consents for the reordering, ...
Read more
With the paint investigation complete, and with the knowledge that ...
Read more
With the slab cast and curing, Messenger proceed with the ...
Read more
With the detail at the column bases resolved, the Limecrete ...
Read more
Within the cathedral reordering masterplan, which vHH undertook in 2008-09, ...
Read more
Our next visit coincides with the Leicester Fabric Advisory Meeting ...
Read more
A couple of months since Messenger’s site set-up, and their ...
Read more
Now that the Old Song School is demolished, the archaeological ...
Read more