Having walked from the station as usual, we are cheered on arrival with the sight of the arm of a concrete pump over the site – finally – and later that day the basement -2 slab being cast by Northfields, Messenger’s chosen groundworks and frame specialist subcontractor.
The first task for the day is to review the condition of the existing stonework at the base of the North porch with Peter Rogan, the Cathedral Architect, and Midland Stone Masonry. It is agreed that Peter will specify the necessary repairs, so that these can take place before the new ramped access inside and outside the porch is installed. This will allow those in wheelchairs or buggies to enter the cathedral from Guildhall Lane, avoiding a long detour to the south entrance in Cathedral Gardens
Within the cathedral, the underfloor heating (UFH) is being installed, zone by zone. Each zone is coordinated with the designed joints in the floor, and with sleeved sections where it is necessary for the pipes to cross joints in the slabs. Within the boiler room, the new pumpsets are being installed, feeding the primary pipework routes to each UFH manifold and radiators.
In the north transept, Messenger are reinstalling the historic ledger slabs that line the walls. These were removed for safekeeping whilst the floor was raised. Using a spider crane, the individual slabs are carefully set on temporary bases, to the right level for the new floor finish, so that new supporting stone sections can be scribed to fit them and the permanent restraints provided.

By the time of our next visit, large areas of ...
Read more
The good weather finds Northfield making good progress with the ...
Read more
The new stone floor is intended to provide a hard-wearing ...
Read more
By June almost all the scaffolding inside the cathedral has ...
Read more
With the underfloor heating loops complete and tested and at ...
Read more
Having walked from the station as usual, we are cheered ...
Read more
Almost a year after it was programmed, and following the ...
Read more
Later in March we are asked to make a second ...
Read more
By March the bulk of the redecoration work to the ...
Read more
By December the scaffold has been removed from the south ...
Read more
During the long period of gaining consents for the reordering, ...
Read more
With the paint investigation complete, and with the knowledge that ...
Read more
With the slab cast and curing, Messenger proceed with the ...
Read more
With the detail at the column bases resolved, the Limecrete ...
Read more
Within the cathedral reordering masterplan, which vHH undertook in 2008-09, ...
Read more
Our next visit coincides with the Leicester Fabric Advisory Meeting ...
Read more
A couple of months since Messenger’s site set-up, and their ...
Read more
Now that the Old Song School is demolished, the archaeological ...
Read more