Within the cathedral reordering masterplan, which vHH undertook in 2008-09, we proposed altering the floor levels to remove the historic steps between the nave and aisles and the spaces further east, with a new floor being installed to distribute services, provide un-stepped access, and improve the appearance of the cathedral. This is an insulated and moisture-open construction, to improve comfort and reduce energy use, and to reduce the tendency for moisture evaporation from, and salt damage to, the stonework of the walls and columns.
The first activity is therefore to remove the floor and reduce levels, under an archaeological brief. This reveals almost no archaeology, except evidence and remains of previous services routes, and their consequent disturbance to the subsoil over the entire area. The reduced levels allow us to provide routes for new services containment, and to give enough depth for the glaspor (foamed glass pebble insulation / capillary break) and limecrete floor slab.
At the abutment of the phase 1 works, to reorder the chancel and crossing to reinter the remains of Richard III, the similar build-up of stone floor, lime mortar bedding, limecrete screed, limescrete slab and glaspor insulation is exposed.
One unwelcome surprise was the discovery that the main arcade piers had been underpinned with concrete, very close to the floor level, which precluded covering them with the limecrete slab, with a casting date already booked in for the Limecrete Company to install.
After some intense dialogue with Price and Myers, the structural engineers, and Messenger, it was agreed to link these pads together with more mass concrete, creating strips along each arcade. By setting these out to align with the floor pattern joints above, we allowed for any relative movement between the limescrete slab and concrete floor to take place at the joint.
The large brickwork services duct is to be reused as our major services run from the boiler room to the north, backfilled but with a series of ducts and chambers giving access to the smaller services runs that issue from it.
Outside the cathedral, the contiguous piled retaining wall for the HLC basements has been installed, and its capping beam cast. This will enable the deep basement void to be excavated by archaeologists without undermining the shallow foundations of the cathedral and the Deanery, both immediately beside it.

By the time of our next visit, large areas of ...
Read more
The good weather finds Northfield making good progress with the ...
Read more
The new stone floor is intended to provide a hard-wearing ...
Read more
By June almost all the scaffolding inside the cathedral has ...
Read more
With the underfloor heating loops complete and tested and at ...
Read more
Having walked from the station as usual, we are cheered ...
Read more
Almost a year after it was programmed, and following the ...
Read more
Later in March we are asked to make a second ...
Read more
By March the bulk of the redecoration work to the ...
Read more
By December the scaffold has been removed from the south ...
Read more
During the long period of gaining consents for the reordering, ...
Read more
With the paint investigation complete, and with the knowledge that ...
Read more
With the slab cast and curing, Messenger proceed with the ...
Read more
With the detail at the column bases resolved, the Limecrete ...
Read more
Within the cathedral reordering masterplan, which vHH undertook in 2008-09, ...
Read more
Our next visit coincides with the Leicester Fabric Advisory Meeting ...
Read more
A couple of months since Messenger’s site set-up, and their ...
Read more
Now that the Old Song School is demolished, the archaeological ...
Read more